This page was exported from Latest Exam Prep [ http://certify.vceprep.com ]
Export date: Thu Nov 14 18:04:10 2024 / +0000 GMT

[Q182-Q200] PRINCE2 PRINCE2-Foundation Dumps Updated [Oct-2024] Get 100% Real Exam Questions!




[Oct-2024] Pass PRINCE2 PRINCE2-Foundation Exam in First Attempt Guaranteed!

Full PRINCE2-Foundation Practice Test and 465 unique questions with explanations waiting just for you, get it now!

NO.182 Which is one of the three levels of plan in PRINCE2?

 
 
 
 

NO.183 Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

 
 
 
 

NO.184 Which of the following describes a use of a Configuration Item Record?

 
 
 
 

NO.185 Which statement is CORRECT about the customer and suppliers of a project in a commercial environment?

 
 
 
 

NO.186 Which role is responsible for appointing the senior user in a project that is independent from a program?

 
 
 
 

NO.187 What process provides the information required to decide whether to authorize the delivery of a project?

 
 
 
 

NO.188 Which of the following statements about the Closing a Project process are true?
1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.
2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.

 
 
 
 

NO.189 In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?

 
 
 
 

NO.190 Which may be funded from a risk budget?

 
 
 
 

NO.191 Which is a factor when deciding the duration of a management stage?

 
 
 
 

NO.192 Why is it necessary to apply the ‘defined roles and responsibilities’ principle?

 
 
 
 

NO.193 Which is a minimum requirement for applying the ‘change’ theme?

 
 
 
 

NO.194 What is an advantage of applying the ‘learn from experience’ principle?

 
 
 
 

NO.195 Which of the following statements about the Project Initiation Documentation are true?
1.The Project Initiation Documentation is used to ensure that a sound basis exists.
2.The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project before the Project Board authorizes a project,

 
 
 
 

NO.196 Which is a purpose of the quality theme?

 
 
 
 

NO.197 What plan is created, and submitted for approval, during the Managing a Stage Boundary process?

 
 
 
 

NO.198 Which statement describes the context of the ‘initiating a project” process?

 
 
 
 

NO.199 Identify the missing words in the following sentence, The six aspects of project performance to be managed are [?] costs, timescales and scope,

 
 
 
 

NO.200 When should the Project Board refer to corporate or programme management for a decision?

 
 
 
 

Get Latest PRINCE2-Foundation Dumps Exam Questions in here: https://www.vceprep.com/PRINCE2-Foundation-latest-vce-prep.html

Post date: 2024-10-29 14:41:03
Post date GMT: 2024-10-29 14:41:03
Post modified date: 2024-10-29 14:41:03
Post modified date GMT: 2024-10-29 14:41:03